Project Activities

Events

Project Timeline

-A +A

The project shall be implemented from Oct 2011 till Oct 2012.

Oct – Dec ‘11

Status quo analysis

Dec ‘11 – Mar ‘12

Prepare WS 1-5

Feb – Mar ‘12

Realize WS 1-5

Apr – May ‘12

Prepare and print guidelines for faculty/students. Conduct CS in MKD/CR

Jun – Aug ‘12

Prepare WS 6 and summarize project results

Aug – Sep ‘12

Public awareness campaign

Sep ‘12

Realize WS 6

Sep – Oct ‘12

Write final report, publish CS outcomes & continue public awareness campaign